Weed Eating Calculator
Length =
Productivity =
Time =
Help
Estimates the number of hours needed to operate a weed eater on a project based on the total linear length in the project.
Rows
- Length: Linear length of the area to weed wack.
- Productivity: Estimated number of linear feet per hour that can be accomplished.
- Time: Amount of time it will take to complete the project.
Examples
Estimate the number of hours it will take to complete a project that includes 208' of space that requires the use of a weed eater. The operator is capable of walking 250 linear feet per hour while performing the task of operating the equipment.
- Length: 208ft
- Productivity: 250ft per hour
It will take approximately 0.832 hours.