Estimate the volume of concrete needed for core filling concrete masonry units (block).
[https://infinitysw.s3.amazonaws.com/cengage/corefilling1.png]
Rows
-Size: Block (size) to be filled.
-#Block: Number of blocks to be filled.
-Bond Beam Size: Bond beam (size) to be filled.
-Bond Beam Units: Units of bond beam to be filled.
Concrete
-Waste: Percentage to factor in to cover waste.
-Block: Total volume of concrete needed to fill the blocks.
-Beam: Total volume of concrete needed to fill the bond beam units.
-Total: Total volume of concrete needed for this project including waste factor.
Examples
How many cubic yards of concrete will be needed to install 1000 square feet of 8×8×16 block and cap it with 20 feet of bond beam? Use 10% waste factor.
-Size: 8×8×16
-#Block: 1,125
-Bond Beam Size: 8×8×16 (Reg)
-Bond Beam Units: 15
Concrete
-Waste: 10.00%
The following results are calculated:
-Block: 10.42
-Beam: 0.12
-Total: 11.59yd³